What distinction does the manufacturer explain?

ABB's AC500 introduction distinguishes an ICD capability description for an IED type, a CID configuration for a concrete IED and an SCD description covering the substation configuration. These are different information scopes, not interchangeable evidence just because each file belongs to SCL engineering.

Substation Drafting is independent and is not affiliated with ABB. This manufacturer introduction is context, not a configuration procedure for every protection relay. Use the actual selected device, engineering tool and approved project documentation.

Sources: ABB: ABB AC500 documentation: IEC 61850 server introduction, checked 21 October 2026

What should the handover register identify?

Keep controlled references within the authorized project environment. Configuration files can contain sensitive system information and should not be posted publicly or sent through an unrestricted general enquiry.

What should the handover register identify?
RecordScope to identifyVerification question
ICDCapability of the relevant typeCorrect product and version?
CIDConfiguration for the specific deviceCorrect IED identity and approved issue?
SCDStation configuration referenceAccepted system baseline?
DrawingAffected device and interface referencesSame engineering revision?
ImplementationAuthorised deployment and test evidenceWhat was actually applied?
Open discrepancyOwner and dispositionWhat still needs confirmation?

How can a complete-looking folder still lack the needed evidence?

Illustrative example. A fictional handover folder contains a manufacturer capability file and a drawing labelled for IED-A. The register marks IED-A's configured communications as verified solely because the file extension is ICD. The record has identified a capability source, not demonstrated the particular approved device configuration.

The reviewer records the missing configuration reference and obtains the designated protection or systems engineer's disposition. Finding a CID or SCD file is also not proof that it was actually installed or tested. The acceptance record must connect the intended baseline with authorized implementation evidence.

How should a file mismatch affect the drawings?

Identify affected device names, communication and signal references before preparing an authorized drawing change. Preserve the original references and accepted revisions. A newer file date does not automatically supersede the controlled project baseline.

Do not rename a file extension, upload a configuration or interrogate an operational IED merely to close this register. Engineering sign-off is performed only by the registered engineer on the job.

Common questions

What else should the bid team know?

Does an ICD establish the installed settings?

No. It describes capability, not proof of actual implementation.

Is an SCD interchangeable with one device's CID?

No. Their stated scopes differ.

Does this worksheet authorise a configuration upload?

No. Use the approved engineering and change process.

Primary sources