Which interfaces need a row?

Start with the project systems and drawing list. Add a row wherever a party needs an input, connection, approval, record or handover from another party.

Substation interface rows
InterfaceInputClosure
Primary to protectionDevice and trip dataApproved schematic
Civil to electricalFoundation and entryReviewed arrangement
Supplier to drafterOutline and terminal dataCurrent vendor file
Construction to testInstalled recordInspection evidence
Test to handoverResult and deficiencyAccepted record

How should an unresolved interface be managed?

State the missing input, affected drawings or work package, owner, due date and interim treatment. Keep responsibility unassigned only as a visible risk.

  • Both parties
  • Source document
  • Required handoff
  • Owner and due date
  • Closure evidence

Why does this help drafting?

A drawing often fails because a boundary is unclear rather than because a line is missing. The register makes that boundary explicit before issue.

Common questions

What else should the bid team know?

What should a substation interface register include?

It should identify both parties, source, handoff, owner, due date, affected drawings and evidence.

Who reviews a substation interface register?

The project lead controls it, with each discipline confirming its own input and acceptance.

Does drafting approve the engineering design?

No. The responsible registered engineer makes design decisions and performs engineering sign-off.

Primary sources

  1. IEEE C2-2023 National Electrical Safety CodeIEEE Standards Association
  2. IEC 61936-1:2021International Electrotechnical Commission
  3. IEC 60617 Graphical Symbols for DiagramsInternational Electrotechnical Commission
  4. 29 CFR 1910.269Occupational Safety and Health Administration