Why does the voltage reference need its own field?

Schneider Electric's Electrical Installation Guide distinguishes voltage between phase and neutral from voltage between phases, using different symbols and circuit expressions. A bare voltage number in a drawing schedule omits that distinction.

Substation Drafting is independent and is not affiliated with Schneider Electric. This guide checks how approved data is represented. It does not select VT connections, change relay settings or prescribe work on an energized circuit.

Sources: Schneider Electric Electrical Installation Guide: Definition of reactive power, voltage definitions and circuit table

What should be traced across the drawing set?

Use the exact VT tag, nameplate or approved submittal, winding information and engineer-approved schematic. Compare each relay or meter input with that same source. Keep residual-voltage quantities separately identified; do not relabel them as a phase voltage to fill a blank.

VT voltage-reference reconciliation worksheet
FieldEvidenceReview action
Primary voltageMagnitude, unit and actual phase referenceDo not mix system and winding bases
Secondary voltageMagnitude, unit and actual phase referencePreserve the approved designation
ConnectionControlled schematic and winding referenceDo not infer from a single number
DestinationRelay or meter input and approved voltage basisReconcile the same signal
Drawing annotationSLD, schematic and schedule revisionResolve inconsistent labels
Open itemMissing basis or conflicting sourceRoute to the responsible engineer

Can the same printed number describe different quantities?

Illustrative example. A fictional schedule labels an input 110 V phase-to-phase. A separate note labels 110 V phase-to-neutral. Even though both numbers read 110 V, the notes describe different connection references. The drafter records a conflict rather than declare the two inputs matched.

The engineer checks the actual approved equipment and connection arrangement. Do not automatically apply a square-root-of-three conversion: its relevance depends on the stated system and winding basis. The example supplies no real voltage rating, relay setting, wiring change or test instruction.

What should the drawing issue record retain?

Preserve the original conflicting sources, engineering disposition and affected sheet revisions. If an approved correction changes the voltage basis, review all linked schedules and input labels rather than alter one visible note. A copied nominal value is not evidence of a compatible relay input.

Engineering sign-off is performed only by the registered engineer on the job. The drafting review does not establish insulation suitability, protection performance, grounding design or permission to operate equipment.

Common questions

What else should the bid team know?

Is the unit V a complete voltage description?

No. Retain the phase reference and approved connection basis.

Do equal printed numbers prove equal voltage inputs?

No. Compare what each number represents.

Should every mismatch be fixed with a square-root-of-three factor?

No. Obtain the approved system and winding basis before any conversion.

Primary sources

  1. Definition of reactive power, voltage definitions and circuit tableSchneider Electric Electrical Installation Guide